Late Start(LS)

البداية المتأخرة

PMBOK 7standardالعربية

Definition

The latest possible point in time when the uncompleted portions of a schedule activity can start without delaying the project finish date.

Synonyms

LS

Category

Schedule

Standards

  • PMBOK 7 PMBOK Guide, 7th Edition

Source references

  • PMBOK 7, Section 6.5.2.2